Project Description
The Sunrise Boulevard Resurfacing Project is part of the City's effort to further their Three-Year Pavement Preservation Plan (PPP) and support economic reinvestment of our commercial corridors.
The Project will resurface Sunrise Boulevard in both directions from Greenback Lane to Madison Avenue. Additionally, Macy Plaza Drive from Sunrise Boulevard to Birdcage Street will also be resurfaced.
The resurfacing treatment will be comprised of multiple layers:
In advance of the resurfacing, City staff completed a targeted mill and fill to address base failures in the pavement.
The project will start with minor edge grinding to prepare the roadway edges for the upcoming resurfacing.
Layer 1 will be Type III Micro-surfacing with a High Polymer content. This will level the roadway, fill voids/cracks, and provide an even surface for the next layer.
Layer 2 will be Polymer Modified Asphalt Rubber Chip Seal. This is a strength layer that will create a complete seal.
Layer 3 will be Type II Micro-surfacing with High Polymer Content. This will provide a finished surface for the roadway, improving the road quality for travelers.
The project will finish by refreshing crosswalks with a colored brick pattern and restripe lane lines, crosswalks, and pavement legends. These improvements will increase visibility for pedestrians and non-vehicle users.
The Project was completed in September 2025.