Solar Energy Permit Electronic Submittal

solarapp

Before applying for an automated solar plan review and solar permit, projects must follow certain requirements. At this time, SolarAPP+ is designed to provide a code-compliance check for the majority of residential, roof-mounted photovoltaic systems. To see which systems are eligible, please refer to the https://solarapp.nrel.gov/docs/SolarAPP-PV-Eligibility.pdf and Eligibility Checklists. Only projects that conform to this list are eligible to use the automated SolarAPP+ portal for instant permitting.

1. Eligibility to use SolarAPP+

  • PV system must be installed on a permitted main dwelling rooftop only (no trenching allowed).
  • If a PV system is required to meet California Energy Code (Title 24) compliance for a new ADU, it must be submitted with the ADU permit and cannot be processed through SolarAPP+.
  • No Ballasted Systems will be allowed to apply through SolarAPP+.
  • No main panel upgrades may be included with the SolarAPP+ application.  If a main panel upgrade is needed, apply for a separate permit.
  • Projects located in the City’s flood zone cannot use SolarAPP+,and must submit applications here. Please check BOTH the FEMA National Flood Hazard Layer (NFHL) Viewer map AND the City’s Flood Plain information page (click here for more information).
  • Must be applied for and issued to a California licensed contractor with C-10, C-46, or B classification (performing two unrelated trades only). The contractor must register with SolarAPP+ before applying for a permit.
  • Permit Runners or “Expediters” are not allowed to submit a SolarAPP+ application without written authorization from the licensed contractor provided to the Building & Safety Division prior to submittal.  
  • Must have a valid CSLB license AND City of Citrus Heights Business License (click here for more information for a business license).
  • For a full list of requirements, please click here.

2. Submit for Automated Review Through SolarAPP+

  • Submit your design to  solarapp.nrel.gov .
  • Click Login or Register to get started.                                                                                 
  • Complete the online application and pay the resulting invoice.  An additional processing fee will be charged by the SolarAPP+ website. 
  • Click here for a demonstration of SolarAPP+

3. Required Documents

  • SolarAPP+ Approval Document
  • Specifications
  • Plans

4. Receiving a Building Permit                                                           

  • Once your SolarAPP+ submission is approved it will be forwarded to the City for review prior to issuing your building permit.
  • City staff may contact you for additional information, if necessary, prior to issuance.
  • If you have not already done so you need to register with the City of Citrus Heights Citizen Access Portal, click here for more information.

5. Getting an Inspection

  • Have your Building inspection card printed and available on-site for an inspector. Lack of documentation on-site is subject a cancelled inspection and a re-inspection fee.
  • Have a one-line diagram and approved plans from Metro Fire (if applicable) on-site for the inspection.  Lack of documentation on-site is subject a cancelled inspection and a re-inspection fee.
  • Click here to schedule an inspection once your project is complete.