Scope & Schedule

About the Project
Due to the size, cost, and availability of funds, the Auburn Boulevard Complete Streets (ABCS) Project has been divided into several phases and segments.  The ABCS Project will include undergrounding of utilities (electrical, communications, etc.) and roadway improvements, also referred to as Complete Streets. Complete Streets includes:
  • Energy-efficient street lights
  • New street trees
  • Bike lanes and sidewalks
  • ADA improvements
  • Aesthetic improvements - stamped cross-walks, benches, and design features
  • Bus pull-outs
  • Pedestrian safety
Click here to view project updates and photos from Phase I of the ABCS project.

Project Schedule

2014
  • July - Phase I (Segment II and III) completed.
2015
  • Begin design and environmental studies.
  • Hold a community meeting to review draft environmental document and preliminary design.
2016
  • Finalize environmental report.
  • Initiate right-of-way negotiations.
  • Hold community meetings.
2017
  • Finalize right-of-way.
  • Apply for construction grant funding.
  • Hold community meetings.
2018-2020
  • Hold community meeting prior to start of construction. 
  • Start construction (pending availability of funds).
  • Hold weekly meetings for businesses and property owners during construction.